What's Needed For A Construction Permit

image1223(6)This article is a text commentary to the service we have successfully delivered, " Obtaining a building permit " . You can look at it in more detail than the state profile.
Or with our other services in connection with the construction of the derivatives

Summary of the Employer: SVT Trans GS, a company whose main business is transport and logistics. In 2012, the owners decided to expand the business and to open a new direction, a network of car service complexes comprising tyre centres, car washing and car service.

Description of the problem. The initial request of the Employer to us was the need to identify and obtain a land plot for the construction of a car wash/car maintenance unit. Complainant

As a result of the work of our specialists, the Employer has obtained a land lease for the construction of a vehicle maintenance facility (with the possibility of automobile, auto-service, tiro-monitoring, auto parts store) for a period of two years.

Вид 2After which, our specialists received a new mission to obtain a building permit.

Method of addressing the challenge

So, the task is to obtain permission for the construction of anatomical/auto-service/schinomontage/magazine on the land area located in the drawing of the Nizhny Novgorod.

1. Obtaining technical conditions. One of the key points in the construction of any capital facility requiring Construction permitthe technical conditions for connection to different communication systems.

Where land is leased through the Investment Board, there is no need to order and obtain technical conditions. All necessary technical conditions for connection to the engineering networks that have been stated in the investment application are attached to the construction plan. This is generally:

  • TUs for the design of the leather sewer;
  • To the list of GP and CC activities;
  • TU for water and sanitation;
  • Opinion from IFRC on the possibility of switching on the declared power;
  • Sometimes (depending on the construction site) this is also an external lighting and a communication line.

(sighs) An important moment. If there is a need for TPs, but they have not been developed and issued at the same time as the land plot and the lease, they must be ordered separately. In addition, our experience shows that frequent TCs have to be adjusted, which is also part of the construction permit work.